When a schedule slips due to supply, labor, or mismanagement, we apportion responsibility and fight for compensation or build your defense across Northern Virginia.
Sources: McKinsey & Company capital-projects analysis; Arcadis 2025 Global Construction Disputes Report.
Delay is one of the most expensive things that can happen to a project, and one of the hardest to untangle. The contract, the schedule, and the daily record decide who absorbs the cost. We turn that paper trail into a claim or a defense.
When a job runs late, the costs pile up fast: extended overhead, idle crews, equipment sitting, and liquidated damages ticking. Acceleration costs money too, because crashing a schedule to recover lost time means overtime, extra crews, and lost productivity.
The hard question is always the same: whose delay was it? Supply chain, weather, labor shortage, a design change, an owner’s slow decision, or a contractor falling behind. The answer is buried in the schedule and the contract, and that is where we work.
We analyze the baseline schedule against what actually happened, separate excusable delays from inexcusable ones, and value time. Then we press the claim for compensation or a time extension, or defend you against a delay claim aimed at you.
Schedule a ConsultationWe separate excusable from inexcusable delay, value the time, and pursue it or defend against it.
Delay outside your control that should extend the deadline without penalty.
The price of speeding up to recover time, including overtime and lost productivity.
Daily penalties for late completion. We challenge or enforce them under the contract.
We compare the plan to what happened to prove cause and apportion the delay.
When more than one party caused the slip, we sort out who pays for what.
Blamed for lost time? We show the real cause and protect you from the cost.
We analyze the baseline against the as-built record to prove what caused the slip.
Float, critical path, overhead, productivity. We know how delay actually plays out on a job.
We put a defensible number on extended overhead, acceleration, and lost productivity.
We pursue compensation and time extensions, or defend you against a delay claim.
Tell us about the project, the contract, and where it went wrong. We find the issues that matter most and the deadlines that apply.
We dig into the documents, the schedule, and the correspondence to find your strongest position.
We file, demand, negotiate, or litigate, with a clear plan and a calendar of every deadline.
We push for the strongest resolution available and are fully prepared to take it to court or arbitration.
“Delay claims are won in the schedule and the daily logs, not in the argument. When a client tells me the job ran six months late, my first questions are: what did the baseline say, what actually happened, and what does the contract require for notice and time extensions? Most of the time the answer is already in the documents, if someone kept them. That is why I push clients to protect the schedule and the record while the job is live. When the fight comes, the side with the cleaner paper trail usually wins.”
Whether the schedule slipped on you or someone is blaming you for it, the schedule and the contract hold the answer. We find it. Serving contractors, owners, and developers across Northern Virginia.