Construction Delay Claim Attorneys in Northern Virginia

Time Is Money on a Job Site. We Decide Who Pays for Lost Time.

When a schedule slips due to supply, labor, or mismanagement, we apportion responsibility and fight for compensation or build your defense across Northern Virginia.

Lost Time Is Lost Money

Delay Is Expensive, and Hard to Untangle

9 in 10
Large projects that finish over budget
~79%
Average cost overrun on large construction projects
12.5 mo
Average time to resolve a North American dispute

Sources: McKinsey & Company capital-projects analysis; Arcadis 2025 Global Construction Disputes Report.

Delay is one of the most expensive things that can happen to a project, and one of the hardest to untangle. The contract, the schedule, and the daily record decide who absorbs the cost. We turn that paper trail into a claim or a defense.

Whose Delay Was It? The Schedule Knows.

When a job runs late, the costs pile up fast: extended overhead, idle crews, equipment sitting, and liquidated damages ticking. Acceleration costs money too, because crashing a schedule to recover lost time means overtime, extra crews, and lost productivity.

The hard question is always the same: whose delay was it? Supply chain, weather, labor shortage, a design change, an owner’s slow decision, or a contractor falling behind. The answer is buried in the schedule and the contract, and that is where we work.

We analyze the baseline schedule against what actually happened, separate excusable delays from inexcusable ones, and value time. Then we press the claim for compensation or a time extension, or defend you against a delay claim aimed at you.

Schedule a Consultation

Where We Come In

  • The schedule has slipped and costs are climbing
  • You were ordered to accelerate and want to recover the cost
  • You are facing liquidated damages for late completion
  • An owner or contractor is blaming you for the delay
  • Supply or labor problems pushed the job past its deadline
  • You need the schedule analyzed to prove what really happened
What We Handle

Delay & Acceleration Claims We Handle

We separate excusable from inexcusable delay, value the time, and pursue it or defend against it.

Excusable Delay

Delay outside your control that should extend the deadline without penalty.

Acceleration Costs

The price of speeding up to recover time, including overtime and lost productivity.

Liquidated Damages

Daily penalties for late completion. We challenge or enforce them under the contract.

Schedule Analysis

We compare the plan to what happened to prove cause and apportion the delay.

Concurrent Delay

When more than one party caused the slip, we sort out who pays for what.

Delay Defense

Blamed for lost time? We show the real cause and protect you from the cost.

Why Contractors and Owners Call Us

We Read the Schedule

We analyze the baseline against the as-built record to prove what caused the slip.

We Speak Construction

Float, critical path, overhead, productivity. We know how delay actually plays out on a job.

We Value the Time

We put a defensible number on extended overhead, acceleration, and lost productivity.

Claim or Defend

We pursue compensation and time extensions, or defend you against a delay claim.

What to Expect

How Working With Us Begins

1

Consultation

Tell us about the project, the contract, and where it went wrong. We find the issues that matter most and the deadlines that apply.

2

Review Contract & Record

We dig into the documents, the schedule, and the correspondence to find your strongest position.

3

Claim or Defend

We file, demand, negotiate, or litigate, with a clear plan and a calendar of every deadline.

4

Resolve or Try It

We push for the strongest resolution available and are fully prepared to take it to court or arbitration.

Anthony I. Shin, Esq., founder of Shin Law Office
Attorney Insight

“Delay claims are won in the schedule and the daily logs, not in the argument. When a client tells me the job ran six months late, my first questions are: what did the baseline say, what actually happened, and what does the contract require for notice and time extensions? Most of the time the answer is already in the documents, if someone kept them. That is why I push clients to protect the schedule and the record while the job is live. When the fight comes, the side with the cleaner paper trail usually wins.”

Anthony I. Shin, Esq.
Founder, Shin Law Office
Common Questions

Answers Before You Call

Who is responsible for a construction delay?
It depends on the cause and the contract. It might be the contractor, a supplier, the owner, the designer, or the weather. We analyze the schedule and the terms to apportion responsibility.
What is the difference between delay and acceleration?
Delay is lost time. Acceleration is the cost of speeding up to make up lost time, often through overtime or added crews. Both can be recoverable depending on the cause and the contract.
What are liquidated damages?
A set daily amount the contract charges for late completion. They can be enforceable, but not always. We challenge them when they are really a penalty or when the delay was excusable.
What is an excusable delay?
Delay caused by something outside your control that the contract treats as grounds for more time, sometimes without extra money. Proving it requires notice and a clear record.
How do you prove a delay claim?
With the schedule. We compare the planned timeline to what actually happened, isolate the critical path, and connect each slip to a cause and a cost.
Does giving proper notice of delay really matter?
Yes, a great deal. Notice provisions are often strict and short. Missing them can sink an otherwise valid claim, so the notice and time-extension record matters as much as the delay itself.

Put a Number on the Lost Time

Whether the schedule slipped on you or someone is blaming you for it, the schedule and the contract hold the answer. We find it. Serving contractors, owners, and developers across Northern Virginia.

Prefer to talk now? Reach Anthony I. Shin, Esq. at 571-445-6565.

Reproduction of any content on this site is prohibited except for individual, non-commercial, informational use. This limited permission does not allow modification, distribution, or incorporation of any content into other works or publications in any medium. You may not reproduce or distribute content from this site to any third party.

Copyright © 2025 Shin Law Office, PLC. All rights reserved.

Powered by HILARTECH

Copyright © 2025 Shin Law Office, PLC. All rights reserved.

Reproduction of any content on this site is prohibited except for individual, non-commercial, informational use. This limited permission does not allow modification, distribution, or incorporation of any content into other works or publications in any medium. You may not reproduce or distribute content from this site to any third party.