What does a construction litigation attorney do?
A construction litigation attorney evaluates and handles disputes involving project contracts, unpaid work, defects, changes, delays, liens, bonds, and procurement decisions. The work can include preserving evidence, preparing notices, negotiating, pursuing or defending claims, and handling court or arbitration proceedings. Contract and document review before a dispute can also help clarify responsibilities and procedures.
Does Shin Law Office represent owners as well as contractors?
The firm’s construction practice serves property owners, developers, general contractors, subcontractors, and suppliers. Representation depends on the matter, conflicts, and an agreed engagement. Share the names of the project participants and explain your role so the firm can assess the appropriate scope of assistance.
What is the deadline to record a mechanic’s lien in Virginia?
Section 43-4 generally requires recording no later than 90 days after the last day of the month in which the claimant last furnished labor or materials, and never later than 90 days after project completion or termination. The statute also limits which amounts may be included through a 150-day lookback, with exceptions. Recording requirements, claimant status, and other notices need separate review. It is not simply 90 days from an unpaid invoice or the last workday.
Is recording a mechanic’s lien the same as enforcing it?
No. Recording and a lawsuit to enforce the lien are separate steps. Under Virginia Code § 43-17, the enforcement period generally ends at the later of six months after recording or 60 days after project completion or termination. That rule does not extend the time to perfect the lien. The filing, parties, property, and other requirements should be reviewed promptly.
Do subcontractors and residential contractors have extra lien notice requirements?
They may. Section 43-7 requires a subcontractor’s written notice to the owner or agent, and the owner’s indebtedness can limit the lien. For qualifying one- or two-family residential work, § 43-4.01 governs notice to a mechanics’ lien agent identified on the permit, generally within a specified 30-day period. Late notice may limit the covered work. Tier, permit information, dates, and exceptions matter.
Can a contractor refuse to pay because the owner has not paid?
For covered private construction contracts, § 11-4.6 generally requires payment to a subcontractor by the earlier of 60 days after receipt of a qualifying invoice or seven days after upstream payment. It restricts pay-if-paid conditions, with an insolvency or bankruptcy exception. Performance, withholding notices, retainage, contract dates, tier, and project coverage still matter. Covered Virginia public contracts follow separate requirements under § 2.2-4354.
Can I recover payment for an unsigned or verbal change order?
Possibly, but the answer depends on the agreement, required notices, authority, communications, conduct, and proof of the extra work and cost. A verbal instruction does not automatically create an enforceable entitlement, and a missing signature does not resolve every case. Preserve the directive, correspondence, daily tickets, pricing, and schedule effects. Residential contract rules also require written, signed changes to specified terms.
Who is responsible for a construction delay?
Responsibility depends on the contract and what caused the delay. Review the affected activities, critical path, concurrent events, notices, available extensions, mitigation, and the evidence supporting added costs. Owner changes, late information, labor or material problems, and weather can involve different allocations of risk. A missed completion date alone does not establish entitlement to delay damages or liquidated damages.
What is a construction acceleration claim?
An acceleration issue arises when work must proceed faster than planned, often through added labor, overtime, shifts, or resequencing. A claim requires review of the instructions, extension requests, contract requirements, causation, and resulting cost. Preserve the schedule versions and records showing why the added effort was required. Merely working overtime does not establish a compensable acceleration claim.
What should I do about defective work or water intrusion?
Address immediate safety and damage concerns, document the condition, and obtain advice about notice, inspection, and preservation before destructive testing or nonemergency repairs. Keep plans, specifications, photographs, inspection findings, warranty communications, and repair estimates. An expert may be needed to assess cause and repair scope. Whether a particular contractor, designer, supplier, or other party is liable depends on the legal duties and evidence.
How long do I have to file a construction lawsuit in Virginia?
There is no single construction deadline. Section 8.01-246 generally gives five years for qualifying signed written contracts and three years for qualifying unsigned or unwritten contracts, subject to other rules. Accrual, goods transactions, defect claims, and the construction statute of repose can change the analysis. Liens, bonds, notices, and procurement protests have separate periods. Do not assume time begins when you discover a problem or that settlement talks extend it.
What is Virginia’s five-year construction statute of repose?
Section 8.01-250 can bar specified injury, property-damage, contribution, or indemnity claims arising from defective and unsafe improvements more than five years after the relevant services or construction. It has important exceptions, including for certain equipment or machinery suppliers and people in possession and control. It is different from a contract limitation period and does not mean every construction claim lasts five years.
What if my contractor has stopped working or left the project?
Keep a record of the work completed, payments, communications, site condition, and remaining scope. Review notice, cure, suspension, termination, warranty, and replacement provisions before acting, while addressing immediate safety needs. A replacement contract or release can affect the remaining dispute. Whether the stoppage is a breach depends on the facts and the agreement, including any payment or access dispute.
Are payment bonds and performance bonds the same?
No. A payment bond addresses qualifying claims for labor or materials. A performance bond concerns the bonded contractor’s performance obligations to the obligee, subject to the bond’s terms and conditions. Obtain the actual bond and identify the parties and project type. Virginia public bonds, federal Miller Act bonds, and private bonds can have different coverage, notice, and filing requirements.
What deadlines apply to a Virginia public payment bond claim?
Under § 2.2-4341, a qualifying claimant with a direct contract with a subcontractor but no contract with the prime contractor generally must give the prime written notice within 90 days after the last labor or materials for which payment is claimed. The statute contains a retainage exception to that notice limit. Suit generally must be filed within one year after the claimant’s last labor or materials. Eligibility, service, and the waiting period before suit also matter. Federal projects use a separate system.
How quickly should I act on a public construction bid protest?
Immediately. Under Virginia Code § 2.2-4360, an award protest generally must be submitted in writing within ten days after the award or announcement of the decision to award, whichever is first. Records-based timing rules, special procurements, available grounds, appeals, and other procedures can change the analysis. Federal and local procedures may differ. Do not assume requesting records or a debriefing automatically preserves every deadline.
What should I check before signing a lien waiver or final release?
Review the amount, payment condition, effective date, through-date, project, rights released, and any exceptions for retainage or unresolved changes. A document labeled “lien waiver” may contain a broader release of contract claims. Compare the language with the money actually being received and the remaining account. Ask for review before signing; do not assume an unpaid balance is automatically reserved.
What belongs in a Virginia home improvement contract?
A useful agreement clearly covers scope, materials, price, payments, timing, permits, changes, warranty obligations, and cancellation rights. Virginia Board regulations require specified written residential terms and disclosures, contractor identification, and signatures before covered work or payments begin, with stated exclusions. Cost-plus and time-and-materials arrangements have specific requirements. Use the actual project and current rules when reviewing a form.
Can you help with a contractor license or a DPOR complaint?
The practice includes contractor licensing and compliance, application or class and specialty questions, and responses to Board matters. Bring the license, contracting entity information, relevant project agreements, and complete DPOR correspondence. License class, specialty, responsible management, designated employee, and qualified-individual requirements can involve different questions. Flag every response and hearing date.
Does a contract’s indemnity clause control every construction loss?
No. Virginia Code § 11-4.1 makes certain construction indemnity provisions unenforceable, and § 11-4.4 separately restricts provisions involving planning or design, including duties to defend. The exact language, parties, type of loss, and applicable law matter. Review insurance policies and endorsements separately; contractual risk transfer does not itself establish insurance coverage.
Can a general contractor be liable for a subcontractor’s unpaid wages?
In qualifying circumstances, yes. Current § 11-4.6(C) addresses covered contracts entered on or after July 1, 2026. It includes a knew-or-should-have-known condition, excludes single-family residential projects, and applies a project-value threshold exceeding $500,000, including qualifying aggregated projects. Contract dates, earlier law, worker records, and the statutory conditions require individual review.
Will my construction dispute go to court or arbitration?
The contract and applicable law may require negotiation, mediation, arbitration, or court proceedings, sometimes in a specified location. Arbitration is not necessarily faster or less expensive, and review of an award can be limited. A dispute-resolution clause also does not answer every question about preserving liens, bond rights, or urgent relief. Bring the entire agreement, including incorporated terms.
What records should I bring to a construction consultation?
Bring the contract and exhibits, a short timeline, project address, participant names, payment history, notices, and the records closest to the issue. Those may include schedules, change orders, daily reports, photographs, inspection findings, delivery tickets, bonds, insurance documents, or court papers. Preserve original electronic files and identify what is missing. You can make contact before your file is complete.
How much does construction representation cost, and where does the firm work?
Fees depend on the scope, complexity, urgency, documents, and dispute process. Discuss the proposed engagement and fee arrangement with the firm; no recovery or fixed outcome is guaranteed. Shin Law Office has offices in Leesburg and Fairfax and serves Northern Virginia, including Loudoun, Fairfax, Arlington, Alexandria, and Prince William. Explain the project location and any pending forum when requesting a consultation.